On the process of commissioning a DUL/DUS, the file transfer for the software basic package is completed and the reload command is executed, what is the next step?
- Set the IP address.
- Format the DUL/DUS.
- Set the clock.
- Begin transferring the upgrade package.
- None of the above.
If you don’t set the time correctly on the DUL/DUS, what is more likely to happen?
- Your DUL/DUS will shut down.
- You will not be able to load the O&M script.
- It puts the license in the outdated state and a license mismatch alarm’ is more likely to come up.
- You will not have connectivity to site.
- None of the above.
Why is it necessary to ‘soft-lock’ the sector/sectors before doing maintenance work such as replacing a DU, RUS, RRUS, AIR or any hardware that will disrupt traffic?
- To ensure NOC and RAN departments will be aware of your work.
- To ensure proper hand-over of traffic to neighboring cells.
- To prevent dropped calls which could negatively impact the site’s performance and the company as a whole.
- To prevent disruption of any ongoing 911 emergency call/s.
- 1, 2 and 3.
- 2, 3, and 4.